Project Plan Phase 2: Week 6

Risk Management and Human Resource Management Plans

Student Name Here

Date

Course Number

Instructor

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Introduction

Projects neither big nor small can be an undertaking to the project team. With a lot of processes involved, things to consider, and steps to accomplish- it easy for one to loose track and get overwhelmed with the flow of things. Part of project management is the incorporation of planning tools that enable the project leaders and team members to conquer and divide tasks, as well as, anticipate and minimize risks. The RACI chart, which stands for Responsible Accountable Consulted Informed chart is instrumental in directing team members to perform specific job functions. The Risk Register, on the other hand, enables the project team to anticipate possible constraints and the likelihood of occurrences. Although directed for two completely purposes, the RACI chart and Risk register when synergistically employed can maintain and improve people and project processes. With improved people and project processes, the success of the project is highly likely.

RACI Chart

One of the common problems encountered in project management involve people process rooting from ambiguity of roles and responsibilities. With major tasks identified and sub tasks involved, not having roles and responsibilities assigned can be make a difference in staff engagement and accountability. RACI chart is an important project management tool that clarifies, identifies and assigns roles; responsibilities and accountabilities that yield improved team productivity and performance (Tartell, 2017). The four major roles presented in the ‘RACI’ chart include: “Responsible,” which refers to the person who does the work; “Accountable,” the person who makes the final decision and approves the step in the project plan; “Consulted,” the person who provides advice or information to those who are responsible and accountable, and “Informed,” the person made aware after the result and decision has been made (Tartell, 2017). The RACI chart presented in Appendix A is constructed using a matrix. The vertical axis list the project tasks, which are broken down to major and minor tasks, while the horizontal axis list the different roles assigned to the team members involved.

Risk Register

Another project management tool that aid in productivity and facilitate project success is the Risk Register. The Risk register is an organized document that contains data results of risks identified, along with its quality and quantity analyses (Chang Han, Su Yuong, Minsuk, 2016). It allows project managers and team members identify possible contingencies that can be encountered and plan for course of action- which makes it a great instrument in preventing issues involving project processes (Chang Han et. al, 2016). The risks on the register are identified using analysis of previous data, interview and lists (Uzulans, 2016). An ID number is assigned to managed individual risks and gain consistency (Uzulans, 2016). The tabular form of a risk register presented in Appendix B is constructed to present the qualitative risk analysis detailing the probability of identified risks occurring, its level of impact to the project. It also illustrates the quantitative analysis with data regarding risk description, risk category and identified triggers. The section on the risk register labeled response enumerates proposed reaction and solutions in the event the risks do present and occur.

Conclusion

To sum things up, project management involves a variety of processes that can overwhelm the project leaders and its team members. Thus, proper utilization of project management tools is important. Two tools presented include the RACI chart and the Risk Register. The RACI chart specializes in clarification of team member roles and responsibilities. It aids in problems with people processes by preventing ambiguous division of labor or tasks and fostering accountability. The Risk register on the other hand, is a tool use to improve the project planning process. It helps identify project risks and provides both quantitative and qualitative analysis to help project managers and their team members prepare and formulate solutions in the event of occurrences. Both RACI chart and Risk register are useful tools in improving project management processes. With appropriate and synergistic use, they can increase the likelihood of project success.

 

 

 

 

 

 

 

 

 

 

 

 

 

Appendix A: Responsible. Accountable, Consulted, Informed (RACI) Chart

 

R=Responsible A=Accountable C= Consulted I=Informed

Project tasks- Major Project Manager

 

SurgiNet team Biomed Go-live team
Project initiation RA
Project Planning RA CI CI I
Site preparation CI RA I
Device Installation CI RA I
Application Construction CI RA
Implementation RI RA I I

 

Project tasks- Minor Project Manager

 

SurgiNet team Biomed Go-live team
Identification of project through evaluation and recommendation

 

RA
Development of project scope document

 

RA
Construction of project charter

 

RA
Obtaining signature and approval for the project charter

 

RA
Selection and formation of the project team RA I I I
Identification of resources and budget proposal

 

RA CI CI CI
Submission of budget for approval

 

RA
Project Kick off Meeting

 

RA I I I
Identification of targeted sites for the SurgiNet Anesthesia Project

 

RA CI CI
Obtaining identified worksite schedules CI RA I
Evaluating rooms for needs such as: outlets, modems, routers

 

I RA I
Finalize schedule for site construction and device installations

 

I RA I
Installation of bedside monitoring equipments

 

CI RA I
Installation of additional Philips monitor

 

CI RA I
Installation of additional outlets, modems and routers

 

CI RA I
Installation of plug in boxes to computer on wheels

 

CI RA I
Meeting with different stakeholders to identify current unit workflows

 

CI RA
Meeting with Anesthesia team to go over unit specific macros

 

CI RA
Construction of Surgi Net Anesthesia macros

 

CI RA
Meeting with different stake holders to identify future unit workflows

 

CI RA
Project management and status meeting

 

R A I I
SurgiNet Anesthesia Application pre-testing

 

I RA
User application training

 

I RA I
SurgiNet Anesthesia Go-live

 

I RA I I

 

Project SurgiNet Anesthesia

Version: 1.0 Date: August 10, 2017

Appendix B: Risk Register

No. Rank Category Risk Description Triggers Potential Response Probability Impact Risk owner Status
1 1 Project risk Rejected project and budget proposal Project may not be a priority considering current restructuring and monetary constraints. Lack of interest and approval from project sponsor Project and budget revision. Low High Project Manager No longer a risk
2 2 Hardware

risk

Delayed equipment purchase and installation Equipment purchase and installation may be delayed due to pending approval, vendor commitment, and site schedule. Equipment or site unavailability, vendor and project team conflict Vendor change, department head meeting with Surgi net team to better coordinate site scheduling. Low Medium SurgiNet team Not occurred, but still a potential

risk.

3 4 Software

risk

 

 

 

Delayed macro construction and completion Delayed macro construction can result from issues with workflow alignment, and stakeholder approval. Conflict of interests between different stakeholders, poor communication, and scattered goals. Kick off meeting and Workflow meeting with stakeholders. Medium High SurgiNet team Not occurred, but still a potential

risk.

4 3 People

risk

Poor Adoption and user readiness Resistance to change and barriers in learning. Lack of learning assessment and information regarding project and impact to current workflow. Communicate project and progress to end-users; perform a learning assessment to plan training. Medium High End Users No longer a risk.

 

 

 

 

 

References

Chang Han, R., Su Yuong, L., Minsuk, S. (2016). Project Risk Management in R& D

organizations: a survey on risk register from Korean companies. Journal of Modern Project Management, 4(2), 10-23.

Tartell, R. (2017). Who does that? Use RACI to figure it out!. Training, (4), 12.

Uzulans, J. (2016). Project risk register analysis based on the theoretical analysis of

project management notion of risk. Economics & Business, 29(1), 43-48.