The design phase of a construction project is expected to take 24 months and the construction
timeframe is also expected to take 24 months. Owner decided to use design-build (DB) project
delivery method and divided the design phase into three (3) equal sub-phases. Similarly, the
construction phase was divided into three (3) equal sub-phases and each sub-phase began
after completion of the corresponding design sub-phase.
- What is the total duration of this project? Show your work in the form of bar diagram.
- What would be total project duration if the owner used typical design-bid-build delivery
method?